Monday of next week, the guys will be in there adding rebar around the bodies of water for the sub decking (under the pavers).
It is also anticipated the coping will be delivered next week and as soon as they receive it, they will be installing it around the pools and spa. The coping right now is the most important aspect of the project right now because everything else (tile, plaster, & pavers) waits on that.