Wolf Creek has applied for all of the required permits to repair the damage caused by the ruptured pipe. We have been advised by our contractor that since this permit requires approval and subsequent inspections from both the Building and Safety Department as well as the Fire Inspector, it is a two week process. Today we are entering the second week of that process. Once the permit is in hand, we estimate it will take 3 to 4 weeks to make the repairs and get them signed off by the inspectors. That timeline is based on known damage. If additional damage is found during the repair process it could extend the timeline. The Association has the majority of contractors already lined up in aware of the timelines. Every effort is being made to reopen the pool for the remaining swim season in late September through October when we usually have a heat wave.