If everything is complete within the ground, (wiring, plumbing, drainage) it is hoped the forms will be complete and the pouring of the sub-deck begins late this week or next early week.
Now that the pool is dry again, repair of 250 linear feet of cracks in the pool will be epoxied and repaired in preparation of new plaster for the pool.
Finally the new pool mechanical equipment is anticipated to be delivered and installation begun. This week sees the end of in ground wiring, plumbing and the beginning of restoration of our pool area. On behalf of the Wolf Creek Board and Avalon Property Management, we appreciate everyone’s patience as we bring an improved pool area for everyone’s enjoyment.