Wolf Creek
  • Home
  • Calendar
  • Docs & Info
  • Contact
  • Updates
  • My Account

Addendum to Week 7 Pool Project Update

3/26/2015

 
Hi everyone:

There have been questions and concerns raised on the unofficial Wolf Creek social media pages regarding the anticipated completion of the pool project.  Some are concerned the pool will not open until sometime in June. Here is the situation as it presents this date.

The pool project had some delays due to the rain and the supplier issues for the coping. Additional problems were found after demolition that required repair. Wolf Creek continues to coordinate with the contractor to find additional steps to make up for lost time.

As I mentioned in the initial Week 7 update, a second crew will be added to install the interlocking pavers in the pool area. This will cut the installation time in half and hopefully make up for the time lost or close to it.

Concerns from residents were also expressed that the timing of the project was poorly planned.  One of the most important factors in determining when to begin the repair is weather. Our pool is utilized and busy up to and through October. The weather is usually warm in October.  Thus, the only dates to start this project without major weather issues is February 1 or beyond.

This project began February 2nd. Even so, we had a week delay due to weather. Starting later in November, December or January is not an option as the weather is damp and extremely cold at night which would impact the curing of the concrete and plaster.

So, when will the project be completed?  I can’t provide a specific date but at the same time I don’t see it being any later than on or near May 1, 2015.  The longest aspect of the project at this point is the 10 days required for the plaster in the pool to cure prior to filling with water. That time is dependent on weather..

I hope this additional information restores the faith of our resident’s that this was well planned. In any construction project of this size, supply delays, weather delays, new problems found requiring additional repair cause delays.

Please keep in mind that repairing someone else’s work is much more difficult to predict than starting a project from the beginning. It is impossible to anticipate all of the problems until you complete demolition and observe what is or is not properly installed. Permits and inspections change as the work order changes occur.

The Wolf Creek Board thanks everyone for their patience as we complete this huge project.  The Board is confident that once you see and enjoy the finished product, you will pleased.


Comments are closed.

    RSS Feed

    Community News:

    Archives

    June 2022
    May 2022
    April 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    June 2021
    May 2021
    April 2021
    March 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    September 2014

    Picture
(951) 699-2918
The Avalon Management Group, Inc. Copyright 2021 ● All rights reserved  ●  Terms of Use ● Privacy Policy
Temecula HOA Management  ● Murrieta HOA Management  ● Menifee HOA Management  ● Lake Elsinore HOA Management  ● Corona HOA Management  ● Wildomar HOA Management  ● Perris HOA Management